School Principal
Mrs Trish Peters
Main Project Contact
Mr Bruce Thompson (ret.)
Project Description
This project will improve water efficiency at Budgewoi Public School by
implementing a range of water saving initiatives. These include installation of
dual flush toilets and spring loaded taps and bubblers. In addition to this,
repairs will be made to existing water tanks, and a new tanks will be installed
to collect rainwater to flush the toilets. These changes will save 357,000
litres of water each year.
Approved Funding
$37,760.11
Completion Report
- 45 spring loaded taps fitted and tested
- 12 cisterns fitted and tested
- All Pumps & Rainbank units fitted and are running toilets.
- All Water tanks delivered & installed.
- Security fencing installed around all tanks and gates secured with locks.
- All tank gauges have been installed.